Project study

Cardinal House, Birmingham

Location

Birmingham

Year

2015

Value

£1.2 million

Duration

20 weeks

How Inco helped

The Cardinal House project involved the full refurbishment of an old dilapidated youth centre into 44 self-contained student accommodation rooms. Each room has its own purpose-made bathroom pod and kitchenette. The works involved the installation of new acoustic partitions built off the newly installed mezzanine structure and foundations. The EPC rating was drastically increased by installing insulated back plasterboard to all the external walls. A completely new M&E installation was carried out to ensure the building conformed to all modern standard living luxuries. The £1.2 million project was carried out in an extremely tight timeframe of 12 weeks.

Managing agent for this project

http://www.citystudent.co.uk/

Next up

Abbeygate Office Works, Reading