CASE STUDY
CHESTER PRIMARY SCHOOL
CHESTER

Flat roof refurbishment across multiple school buildings.
A six-week programme of flat roof refurbishment works has transformed roofing across multiple buildings at a primary school in Chester. Delivered entirely during the school holidays, the project combined targeted roofing upgrades with improved thermal performance, providing long-term protection for the school estate without disrupting the academic calendar.

PROJECT LOCATION
Chester
CONSULTANCY
WGM Building Consultancy
PROGRAMME
6 weeks
SECTOR
Education
SCOPE OF WORKS
The refurbishment involved a combination of overlay and full strip-off roofing techniques, tailored to the requirements of the different roof areas.
Alongside the roofing works, thermal upgrades were incorporated to reduce heat loss and improve the buildings' energy performance. The result is a series of renewed roof areas designed to provide reliable weather protection for years to come.

About
PROJECT DELIVERY
Working within a six-week school holiday programme, careful coordination was key to delivering the refurbishment across multiple buildings.
The works were planned to make full use of the available holiday period, allowing the roofing upgrades to progress without interrupting teaching or day-to-day school activities.
The programme was completed ahead of pupils and staff returning for the new term.
PROJECT OUTCOME
The school now benefits from refurbished flat roofs with improved thermal efficiency and long-term weather protection.
Completed within the allocated programme, the project has addressed essential building maintenance requirements while supporting the continued use and performance of the school estate.