CASE STUDY
SURREY PRIMARY SCHOOL
SURREY

Comprehensive roof upgrades across a primary school.
A programme of flat roof refurbishment works was completed across multiple buildings at a primary school in Surrey, forming part of the school’s wider modernisation and improvement programme. The project combined tailored overlay and full strip-off roofing solutions to improve thermal performance, durability and energy efficiency, with works carefully planned to minimise disruption to the school’s day-to-day activities.

PROJECT LOCATION
Surrey
CONSULTANCY
WGM Building Consultancy
PROGRAMME
3 months
SECTOR
Education
SCOPE OF WORKS
The project involved a programme of flat roof upgrades across multiple buildings at a primary school in Surrey.
A tailored combination of overlay and full strip-off roofing systems was delivered across the site, providing the most appropriate solution for the different roof areas while improving durability, performance and lifespan.

About
PROJECT DELIVERY
Completed between summer and autumn 2025, the works were carefully programmed around the operational needs of the school.
Key works were undertaken during school holiday periods, allowing the programme to progress safely and efficiently while ensuring zero disruption to teaching and learning.
PROJECT OUTCOME
The completed works have provided the school with upgraded, longer-lasting roofing systems, alongside improvements to thermal performance and energy efficiency.
Delivered without disruption to pupils or staff, the project supports the school’s wider modernisation and improvement strategy while creating a more comfortable and sustainable learning environment for the school community.